BULGARIAN TECHNICAL TWINNING PROGRAM
PAZARDJIK, BULGARIA WEST BEND, WI PARTNERSHIP
January 26, 2001I. Introduction
In order to implement the activities in the Memorandum of Understanding, the Municipality of Pazardjik, Bulgaria and the City of West Bend, Wisconsin have agreed to the following double anchor strategy. It will serve as the framework for the on-going relationship between the two partner cities. The Action Plan specifies the short-term goals for cooperation between the resource cities, which can be successfully accomplished within the next 13 months in the primary areas of cooperation. It also lays out the long-term goals, which will get accomplished after the current USAID supported program is completed.
The partnership has defined its primary and secondary areas of cooperation as follows:
Primary areas:
A. Economic Development
B. Energy Efficiency-Environment
Secondary areas:
C. the Functioning of the Municipality/City Administration,
D. the Municipal/City Transportation System,
E. Waste Management, and
F. Social Policy Issues
II. Project Implementation
Chart 1.
Areas of Cooperation
Technical Projects
Pazardjik
Counterpart
West Bend Counterpart
1. Economic Development
1. Create a business development plan for Pazardjik s economic development zone
Ivan Kolchakov
Dimitar Petkov
Georgi Gaidarov
Dennis Melvin
John Capelle
Mark Piotrowicz
2. Environment
2. Develop a Request For Proposal for the development of Ostrova Park
Deputy Mayor Bandeva
Chief Ecologist
Steve Scharrer
3. Functioning of the Municipality/ City Administration,
GIS
3. Develop a management plan to create a Geographic Information System for the city.
Dimitar Petkov
Chief Architect
Mark Piotrowicz
A. Economic Development
TECHNICAL PROJECT #1: Create a business development plan for Pazardjik s economic development zone
Goal:
Short Term: Establish a special business zone which will create a favorable environment for business development.
Long Term: Create a favorable business climate for Pazardjik to attract investments.
Expected Outcome
Action Steps
Time Frames
Responsible Party
Explain to West Bend what has been achieved to date.
(Including: maps, data, and description of the business site)
Feb. 15, 2001
Dimitar Petkov
Create a business survey template.
Feb. 28, 2001
John Capelle
Determine types of small and midsize businesses to be developed.
(Including a survey of existing businesses in Pazardjik)
Mar. 15, 2001
Georgi Gaidarov
Publish an Economic Development Zone plan.
Mar. 15, 2001
John Capelle
Georgi Gaidarov
Create a marketing plan for the economic development zone.
July 31, 2001
John Capelle
Investigate business financing options for the economic development zone.
Oct. 31, 2001
John Capelle
Ivan Kolchakov
Determine any necessary administrative reorganization in Pazardjik in order to implement the project.
Dec. 31, 2001
Ivan Kolchakov
Coordinate the financing and completion of infrastructure.
Sept. 21, 2001
John Capelle
Georgi Gaidarov
Identify cooperative efforts with other local governments in the regional economic development zone.
July 31, 2001
John Capelle
Ivan Kolchakov
Identify foreign investment opportunities of West Bend and Wisconsin businesses in Pazardjik.
Dec. 31, 2001
Dennis Melvin
John Capelle
Creation of an economic development zone in Pazardjik.
B. Environment
TECHNICAL PROJECT #2: Develop a Request For Proposal for the redevelopment of Ostrova Park
Goal:
Short Term: To develop a Request for Proposal (RFP) by the end of 2001.
Long Term: Redevelopment of Ostrova Park for recreational purposes.
Expected Outcome
Action Steps
Time Frames
Responsible Party
Collect existing development concepts.
April, 2001
Deputy Mayor Bandeva
Chief Ecologist,
R. Metodieva
Review and recommend existing development concepts.
May-July 2001
Steve Scharrer
Develop RFP.
Dec. 31, 2001
Deputy Mayor Bandeva
Chief Ecologist,
R. Matodieva
The creation of an RFP for the redevelopment of Ostrova Park.
C. City AdministrationTECHNICAL PROJECT # 3: Develop a management plan to create a Geographic Information System (GIS) for the city.
Goal:
Short Term: Create the capacity within the Pazardjik municipal government to implement GIS.
Long Term: Improve the accessibility and availability of spatial information in support of the decision making process.
Expected Outcome
Action Steps
Time Frames
Responsible Party
Needs analysis
1. Create survey form
2. Create analysis matrix
3. Review survey results
Feb. 15, 2001
April 2001
April 2001
Mark Piotrowicz
Mark Piotrowicz
Dimitar Petkov
Chief Architect, Christo Gerasimov
Development of general system design.
July 31, 2001
Mark Piotrowicz
Dimitar Petkov
Provide descriptions of GIS coverages.
July 31, 2001
Mark Piotrowicz
Creation of the Pazardjik system.
Oct. 31, 2001
Dimitar Petkov
Chief Architect, Christo Gerasimov
Ongoing technical support.
Dec. 31, 2001
Mark Piotrowicz
A GIS management plan including documents describing how the spatial information should be organized, collected, maintained, managed and shared.
The training of a Pazardjik staff person to organize and implement GIS.
IV. Schedule of Technical Exchanges
Participants
Destination
Dates
Technical Project
John Capelle, Mark Pietrowicz, TBD
Pazardjik
March
all
Christo Gerasimov,
Christo Kalvachev, TBD
West Bend
July
all
John, Mark, TBD
Pazardjik
September
all
Mrs. Bandeva, Ms. Metodieva, TBD
West Bend
December
all
TBD
Pazardjik
TBD
all
______________________________ ____________________________________
Ivan Kolchakov Michael Miller
Mayor of Pazardjik Mayor of West Bend
______________________________ ____________________________________
Antoaneta Mateeva Judit Deilinger
Program Specialist Partnership Manager
FLGR ICMA